Electrical Work at Salli Kaadu – New Build
Monday, 11th August 2025 - Morning
At Ravi’s request, Senthuran Electrician and his helper, Jeyakumar, attended Salli Kaadu to commence the electrical installation for the new build. They arrived on site at 9.15 am and immediately contacted Ravi to receive initial instructions. A generator was arranged to provide the necessary power supply for their work.
As several details required in-person clarification, we visited the site to provide guidance on the precise positioning of plug points, light switches, and fan switches. Each location was discussed thoroughly to ensure practicality and alignment with the building layout. Senthuran confirmed his full understanding of the requirements and the intended design.
We departed the site at 11.30 am, leaving Senthuran and Jeyakumar to proceed with the installation work as planned.
Summary:
Electrical installation work began at the Salli Kaadu new build, with Senthuran and Jeyakumar receiving both remote and in-person instructions. Key switch and plug point placements were finalised on-site before the team continued independently.