Plasterers: Commencement of Plastering Work at Salli Kaadu

Commencement of Plastering Work at Salli Kaadu
Thursday, 7th August 2025 — Morning

Mason Thuvarakan and his team of four people began plastering the first room at Salli Kaadu. The preparation work included watering down the walls to ensure the new plaster would adhere properly. Due to the very high ceiling, this room is expected to take approximately two to three days to complete.

Payments were made as follows:

  • Rs. 7,000 to T. Mohanathas

  • Rs. 7,000 to Thuvarakan

Summary: Thuvarakan’s team commenced plastering the first room after proper preparation. Payments to key workers were completed. Estimated completion time is two to three days due to the room’s high ceiling.