Seelan worked alongside Mason Thuvarakan throughout the day, bricking in and sealing the gap between the walls and the new roof extension at the front of the new build.
Mohan visited PTK to manage the dogs and then cut overhanging branches along the border between Bharathy and our property at Ravi’s request. He later left to attend to morning chores at SK. After lunch, Mohan assisted at the new build by loading large stones into the tractor trailer, which Seelan had moved to the front of the road.
Electrician Senthuran and his helper were on site and carried out their scheduled work.
Gobi, the carpenter, worked on the roof extension and completed the task by 2:00 pm. He was paid LKR 21,000 for his work.